Question #6413702Single Choice

Algebra-1

Question

A project manager hires 6 workers to complete a task in 10 days. After 4 days, 2 workers leave. Assuming each worker has the same work efficiency, how many extra days will be needed to complete the task?

Options

A
    2 days
B
    3 days
C
    6 days
D
    9 days

Answer & Analysis