The formula below is often used by project managers to compute E, the estimated time to complete a job, where O is the shortest completion time, P is the longest completion time, and M is the most likely completion time.

Which of the following correctly gives P in terms of E, O, and M?

Which of the following correctly gives P in terms of E, O, and M?
Options
A
P = 6E - O - 4M
B
P = -6E + O + 4M
C

D

Answer & Analysis
Click "Show Answer" to reveal the answer and analysis